The money, and where it stalled
Every State Has a Plan. Not Every Plan Has Broken Ground.

Feasibility studies are public records, and most of them cite the same handful of towns.
Photo: Artem Podrez / Pexels
The NTIA's BEAD approval gauntlet, state by state
The Infrastructure Investment and Jobs Act of November 2021 authorised $42.45 billion for the Broadband Equity, Access, and Deployment programme, administered by the National Telecommunications and Information Administration. Nearly four years later, construction has begun in only a handful of jurisdictions. The gap between appropriation and groundbreaking is not an accident; it is the structure of the programme itself.
BEAD requires each state or territory to clear a staged federal approval process before a single subgrantee can execute a construction contract. The sequence runs: an initial proposal volume one, an initial proposal volume two, then a final proposal, then NTIA approval, then state subgrant awards, then permitting, then build. Every stage is an opportunity for delay, and most states have found that opportunity at multiple points.

A library's public-computing shelf. The institution was an access point before home broadband was the ordinary case.
Photo: Pixabay / Pexels
How the approval process works — and where it stalls
The first stage, Initial Proposal Volume 1, required each eligible entity to submit its five-year action plan, its local coordination documentation and its challenge process procedures. The NTIA's BEAD program status tracker, updated through mid-2025, shows that all fifty states, the District of Columbia and the five territories have received Initial Proposal Volume 1 approval. That milestone, though universal, masked substantial divergence: some states cleared it in 2023, others not until well into 2024.
Initial Proposal Volume 2 is where the process becomes technically demanding. States must submit subgrantee selection criteria, scoring rubrics, speed-test and challenge process results reconciled against the FCC's national broadband map, and detailed project cost estimates. As of the NTIA's most recently published status data, the majority of states have received Volume 2 approval, but a significant cohort — concentrated in the South and in states that entered lengthy internal disputes over fibre-versus-fixed-wireless technology weighting — remained under NTIA review into 2025.
The final proposal is the binding document: it names actual subgrantees, specifies covered locations, and locks the funding amounts. As of mid-2025, according to NTIA published approval records, fewer than fifteen states had received final proposal approval. Virginia was among the first to reach that threshold, as was Louisiana. Nevada, whose Office of Science, Innovation and Technology moved with relative speed through the subgrant selection process, also received early final proposal approval. The majority of states were still at or between the Volume 2 and final proposal stages.
The challenge process, required under BEAD before any final proposal can be submitted, deserves particular attention. Each state must administer a formal procedure by which ISPs, local governments and individual address holders can contest the FCC broadband map's characterisation of a location as already served. Because BEAD formula allocations — the dollar amounts apportioned to each state before planning began — derived directly from those map counts, states discovered that a successful challenge process could reshape their own budgets. Texas, with one of the largest unserved-location counts in the country, ran a challenge process that modified tens of thousands of address determinations. That process took months. It was required. It pushed the final proposal further out.
State variation: the leaders and the laggards
No two states are on identical timelines, and the NTIA has been careful not to publish a ranked table of states by progress. What its status tracker does make legible is a rough clustering.

BEAD is administered through the Department of Commerce, which is why approval is a federal step before a state one.
Photo: broadbandusa.ntia.gov
A leading cohort — including Louisiana, Virginia, and a small number of upper-midwestern states — received final proposal approval and began issuing subgrant awards in late 2024 or early 2025. Louisiana's path was eased in part by LUS Fiber's long operational history: state broadband officials had institutional knowledge of fibre construction costs and governance structures that many states lacked. That is not a transferable asset; it reflects decades of prior public investment.
A middle cohort, encompassing the largest share of states, completed Volume 2 review and submitted or revised final proposals in 2024 and 2025. These include states with large rural footprints — Minnesota, West Virginia, Mississippi — where the engineering complexity of reaching dispersed unserved locations is genuine, not administrative. West Virginia's broadband development office faced the additional complication of terrain-driven cost uncertainty that forced multiple rounds of cost-reasonableness review with the NTIA before final approval could proceed.
A trailing cohort drew sustained attention from broadband advocates and congressional overseers. Several states — most prominently those that initially weighted fixed wireless access and LEO satellite service heavily in their scoring rubrics — were required by the NTIA to revise their technology prioritisation. The IIJA's statutory preference for fibre-to-the-premises gave the NTIA authority to push back on proposals that treated fixed wireless as functionally equivalent to fibre, and it used that authority. States that had to rewrite subgrantee selection criteria, re-score eligible applications and resubmit Volume 2 lost six to twelve months.
The territories face a structurally distinct situation. Puerto Rico received a BEAD allocation of approximately $334 million, and its process was complicated by the interaction of BEAD requirements with ongoing federal oversight mechanisms stemming from prior disaster-recovery grants. The U.S. Virgin Islands, Guam, American Samoa and the Commonwealth of the Northern Mariana Islands received smaller allocations and, as of mid-2025 NTIA status data, had made variable progress through the approval stages.
What approval actually authorises — and what it does not
Receiving final proposal approval from the NTIA does not mean fibre is in the ground. It means the state may execute subgrant agreements with selected ISPs, municipalities or electric cooperatives. Those subgrantees must then complete their own environmental and historic preservation reviews under the National Environmental Policy Act and the National Historic Preservation Act, negotiate pole attachment and rights-of-way agreements with utilities and local governments, secure construction crews — a genuine constraint in a post-pandemic labour market — and begin pulling fibre. Industry analysts and state broadband officials have consistently projected that meaningful construction at scale will not be widespread until 2026 in even the most advanced states, with many projects completing in 2027 or 2028.
The NTIA, under former administrator Alan Davidson, communicated repeatedly that speed was a priority — but the agency's own compliance requirements and the statutory framework written into the IIJA constrain how fast any compliant state can move. Oversight bodies including the Government Accountability Office have examined the programme's administrative architecture and noted the inherent tension between accountability requirements and deployment velocity. The Benton Institute for Broadband and Society and the Institute for Local Self-Reliance have each published analyses arguing that streamlining state-level procurement processes is the most available lever for acceleration now that most states have cleared early NTIA review.
The political context shifted in early 2025. With a change in administration and questions about federal programme prioritisation, BEAD's trajectory came under scrutiny. The NTIA's published status tracker continued to reflect approvals through mid-2025, but the pace of final proposal reviews became a subject of active monitoring by congressional Democrats including members who had championed the original legislation.
The $42.45 billion has been appropriated. The plans exist. The approval machinery has moved, unevenly, across fifty states, the District of Columbia and five territories. The question that determines whether unserved households in rural Appalachia, the Navajo Nation or the Mississippi Delta see a fibre strand in the next three years is not whether there is money — it is whether the distance between approved plan and completed network can be closed before the political conditions that made the programme possible shift again.